Hi, i would like to request the following:
- status of right-of -way including number of informal settlers and percentage relocated) in each of the following projects of DPWH (Metro Manila Skyway 3, NLEX - SLEX Connector Road , Bonifacio Global City to Ortigas Road Link Project, Sta. Monica , Nlex Harbor link, Segment 10, Cavite - Laguna Expressway and Laguna Lake Highway
- budget for right-of-way for each of the DPWH projects mentioned above
A.SANTIAGO
March 12, 2018, 3 p.m.
March 12, 2018
Dear BRENDA,
Thank you for your request dated Mar 09, 2018 under Executive Order No. 2 (s. 2016) on Freedom of Information in the Executive Branch, for right of way statistics on projects implemented by DPWH.
We received your request on Mar 09, 2018 and will respond on or before Mar 30, 2018 06:52:27 PM, in accordance with the Executive Order's implementing rules and regulations.
Should you have any questions regarding your request, kindly contact me using the reply function on the eFOI portal at https://www.foi.gov.ph/requests/aglzfmVmb2ktcGhyHgsSB0NvbnRlbnQiEURQV0gtMzAyNjYzODk3NTQxDA, for request with ticket number #DPWH-302663897541.
Thank you.
Respectfully,
Andro Santiago
FOI Officer
B.VALLARTA
April 10, 2018, 3:03 p.m.
Good afternoon! I'd like to followup on this request.
May i know the current status of this request?
Thank you,
Brenda Barrientos-Vallarta
W.SACABON
May 11, 2018, 3:03 p.m.
May 11, 2018
Dear BRENDA VALLARTA,
Greetings!
Dear BRENDA,
Thank you for your request dated Mar 09, 2018 under Executive Order No. 2 (s. 2016) on Freedom of Information in the Executive Branch, for right of way statistics on projects implemented by DPWH.
Based on the data submitted by Director Alex Bote, Public Private Public Partnership Service, please be informed that, to date, the right-of-way acquisition status of Metro Manila Skyway Stage 3 Project, NLEX-SLEX Connector Road, NLEX Harbor Link, Segment 10 and Cavite-Laguna Expressway is on-going.
Here under is the tabulated estimated number of informal settlers, status of relocation and the FY 2018 approved budget for the right-of-way acquisition of the above-mentioned projects.
PROJECT
APPROXIMIATE NUMBER OF INFORMAL SETTLER FAMILIES
STATUS OF RELOCATION
FY 2018
RIGHT-OF-WAY FUNDS
1. MMSS3 300 Ongoing discussion with National Housing Authority (NHA) The budget for MMSS3 project is shouldered by the concessionaire.
2. NLEX-SLEX Connector Road 4000 Ongoing discussion with NHA Php 2,935,000,000.00
3. NLEX Harbor Link, Segment 10 3000 100% relocated. Php 1,263,381,000.00 (Lump sum for the Manila North Expressway Project, Segments 8.1,8.2,9 and 10)
4. CALAX None N/A Php 8,006,576,000.00 (Lump sum for DPWH PPP Projects)
Lastly, the Bonifacio Global City to Ortigas Road Link Project and Laguna Lake Highway are implemented by the UPMO-RMC1 and National Capital Region of the DPWH, respectively.
Should you have any questions regarding your request, kindly contact me using the reply function on the eFOI portal at https://www.foi.gov.ph/requests/aglzfmVmb2ktcGhyHgsSB0NvbnRlbnQiEURQV0gtMzAyNjYzODk3NTQxDA, for request with ticket number #DPWH-302663897541.
Thank you.
Respectfully,
Andro Santiago
FOI Officer
Is this request offensive?
Requests for personal information and vexatious requests are not considered valid requests for Official Information.
If you believe this request is not suitable, you can report it for attention by the site administrators.