Hi! I'm Moses, I would like to request excel data in regards to this information:
1. Latest Construction Materials Price Data
Thank you very much!
A.SANTIAGO
June 2, 2021, 12:25 p.m.
June 2, 2021
Dear Moses,
Thank you for your request dated Jun 02, 2021 under Executive Order No. 2 (s. 2016) on Freedom of Information in the Executive Branch, for Latest List of Construction Materials Price Data.
We received your request on Jun 02, 2021 and will respond on or before Jun 23, 2021 12:06:41 PM, in accordance with the Executive Order's implementing rules and regulations.
Should you have any questions regarding your request, kindly contact me using the reply function on the eFOI portal at https://www.foi.gov.ph/requests/aglzfmVmb2ktcGhyHgsSB0NvbnRlbnQiEURQV0gtMjc2NTkwMTE2MDM4DA, for request with ticket number #DPWH-276590116038.
Thank you.
Respectfully,
Andro Santiago
FOI Officer
M.PENAFLOR
June 18, 2021, 12:45 p.m.
Hi,
Good day!
I would like to follow up my request for the updated list of Construction Materials Price Data.
Thank you very much,
Moses B Penaflor
M.PENAFLOR
June 23, 2021, 10:14 a.m.
Hi,
Good day!
I would like to follow up my request for the updated list of Construction Materials Price Data.
Thank you very much,
Moses B Penaflor
M.PENAFLOR
June 24, 2021, 3:16 p.m.
Hi,
already due but no email yet? can i get atleast a reply from your good office?
Thank you verymuch!
Moses Penaflor
M.PENAFLOR
July 13, 2021, 3:22 p.m.
Hi!
I would like to follow up my ticket number #DPWH-276590116038.
Because its over due and no response and no update at all.
I hope I will get a response soon.
Thank you!
W.SACABON
July 24, 2021, 9:18 a.m.
Dear Mr. Moses Penaflor,
Greetings!
This refers to your letter, dated July 14, 2021, requesting for a copy of the Construction Materials Price Data (CMPD) for the utilization in the feasibility study for potential investment.
As per memorandum, dated July 14, 2021, of OIC-Director Andro V. Santiago, Stakeholders Relations Service, DPWH FOI Receiving Officer, endorsing that your request complies with the provisions of Executive Order No. 2, series of 2016, also known as the Freedom of Information Order. In this regard, here is the link of the latest approved Nationwide CMPD (2nd Quarter of C.Y. 2021):
https://drive.google.com/drive/folders/1ypXiDirOyy7PS3JMketGztKPZqhaa0Ev?usp=sharing.
Furthermore, the said CMPD was evaluated and generated by the Central Office – Technical Working Group (CO-TWG) and approved by the Director of the Bureau of Construction and checked for its reasonableness. However, further validation is advised prior to application.
Very truly yours,
Ezekiel M. Alcantara
Engineer II
Pre-Construction Division, Bureau of Construction
Department of Public Works and Highways
Tel. # Direct Line (02) 5304.3396; Local No. 43396 | www.dpwh.gov.ph
Is this request offensive?
Requests for personal information and vexatious requests are not considered valid requests for Official Information.
If you believe this request is not suitable, you can report it for attention by the site administrators.