Published by Department of Energy(DOE) on Oct. 10, 2023.
Requested from DOE by G. Almonte at 06:57 PM on
Oct. 10, 2023.
Purpose: Research
Date of Coverage: 10/10/2020 - 10/10/2023
Tracking no: #DOE-363707614216
G.ALMONTE
Oct. 10, 2023, 6:57 p.m.
Hi! I would like to request information regarding:
1. Existing solar and wind projects in the Philippines with location and generation capacity
2. Corresponding construction, permit, and operational costs of the project
3. LCOE of the project
Thank you!
R.DIVISION
Oct. 15, 2023, 2:26 p.m.
October 15, 2023
Dear Citizen,
Thank you for your request dated Oct 10, 2023 under Executive Order No. 2 (s. 2016) on Freedom of Information in the Executive Branch, for Cost of Solar and Wind Projects.
We received your request on Oct 10, 2023 and will respond on or before Oct 31, 2023 06:57:14 PM, in accordance with the Executive Order's implementing rules and regulations.
Should you have any questions regarding your request, kindly contact me using the reply function on the eFOI portal at https://foi.gov.ph/requests/aglzfmVmb2ktcGhyHQsSB0NvbnRlbnQiEERPRS0zNjM3MDc2MTQyMTYM, for request with ticket number #DOE-363707614216.
Thank you.
Respectfully,
Imelda M. Roxas
Records Management Division
DOE FOI Receiving Officer
R.BUREAU
Oct. 25, 2023, 9:44 a.m.
October 25, 2023
Dear Gio Jerson Almonte,
Greetings!
Thank you for your request dated Oct 10, 2023 06:57:14 PM under Executive Order No. 2 (s. 2016) on Freedom of Information in the Executive Branch.
Your request
You asked for Cost of Solar and Wind Projects.
Response to your request
We wish to provide you with our response, accordingly:
1. Existing solar and wind projects in the Philippines with location and generation capacity
Answer: https://www.doe.gov.ph/electric-power/list-existing-power-plants-july-31-2023?q=list-existing-power-plants
2. Corresponding construction, permit, and operational costs of the project:
Solar and Wind Project Cost:
Roof-mounted Solar - 48,727,311.33
Ground-mounted Solar - 49,473,854.00
Floating Solar - 56,196,155.60
Onshore Wind - 81,662,013.85
3. LCOE of the project:
https://www.doe.gov.ph/renewable-energy/ready-renewables-grid-planning-and-competitive-renewable-energy-zones-crez
or
https://www.nrel.gov/docs/fy20osti/76235.pdf
Your right to request a review
If you are unhappy with this response to your FOI request, you may ask us to carry out an internal review of the response by writing to the DOE Secretary Your review request should explain why you are dissatisfied with this response, and should be made within 15 calendar days from the date when you received this letter. We will complete the review and tell you the result within 30 calendar days from the date when we receive your review request.
If you are not satisfied with the result of the review, you then have the right to appeal to the Office of the President under Administrative Order No. 22 (s. 2011).
Thank you.
Respectfully,
Renewable Energy Management Bureau
FOI Officer
G.ALMONTE
Oct. 25, 2023, 10:46 a.m.
Hi! Regarding the costs, do you have a detailed breakdown for this? And also what are the capacities of these plants. Would be happy to receive more information about the plants.
Is this request offensive?
Requests for personal information and vexatious requests are not considered valid requests for Official Information.
If you believe this request is not suitable, you can report it for attention by the site administrators.